Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.588 | 95,019 | 55,871 |
Arena lavada de río 6 m3 | 0.0980196 | 570,000 | 55,871 |
Cemento 1 Kg | 367.5 | 798 | 293,265 |
Cemento, bulto de 50 Kg | 7.35 | 39,900 | 293,265 |
Triturado de 3/4" x 1 m3 | 0.882 | 150,500 | 132,741 |
Grava 3/4" x 6 m3 | 0.14700000294 | 903,000 | 132,741 |
Agua para la obra 1 litro | 199.5 | 36 | 7,262 |
Salario mínimo mensual vigente, base | 0.005586 | 1,300,000 | 7,262 |
Valor Adicional: | 489,139 |
| $793,300 |
| $1,070,000 |
| $260,000 |
| $1 |
| $1,168,250 |
| $1,668,500 |
| $19,800 |
| $1 |
| $338,000 |
| $690,800 |
| $103,612 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 4.5 | 5,200 | 23,400 |
Salario mínimo mensual vigente, base | 0.018 | 1,300,000 | 23,400 |
Transporte 1 tonelada x 1 kilómetro | 0.04 | 3,900 | 156 |
Salario mínimo mensual vigente, base | 0.00012 | 1,300,000 | 156 |
Valor Adicional: | 23,556 |
| $165,750 |
| $371,000 |
| $69,900 |
| $97,500 |
Subtotal: $7,349,469