| $175,800 |
| $36,800 |
| $2,740,000 |
| $2,800,000 |
| $30,800 |
| $469,700 |
| $20,000 |
| $544,900 |
| $199,700 |
| $35,500 |
| $155,150 |
| $294,970 |
| $672,283 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 1.0185 | 95,019 | 96,777 |
Arena lavada de río 6 m3 | 0.16978395 | 570,000 | 96,777 |
Cemento 1 Kg | 656 | 798 | 523,488 |
Cemento, bulto de 50 Kg | 13.12 | 39,900 | 523,488 |
Agua para la obra 1 litro | 328.12 | 36 | 11,944 |
Salario mínimo mensual vigente, base | 0.00918736 | 1,300,000 | 11,944 |
Valor Adicional: | 632,208 |
| $492,210 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Agua para la obra 1 litro | 179 | 36 | 6,516 |
Salario mínimo mensual vigente, base | 0.005012 | 1,300,000 | 6,516 |
Arena lavada de río 1 m3 | 0.756 | 95,019 | 71,834 |
Arena lavada de río 6 m3 | 0.1260252 | 570,000 | 71,834 |
Cemento 1 Kg | 315 | 798 | 251,370 |
Cemento, bulto de 50 Kg | 6.3 | 39,900 | 251,370 |
Triturado de 3/4" x 1 m3 | 0.756 | 150,500 | 113,778 |
Grava 3/4" x 6 m3 | 0.12600000252 | 903,000 | 113,778 |
Valor Adicional: | 443,498 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $130,000 |
| $91,000 |
| $97,500 |
| $682,471 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 420 | 798 | 335,160 |
Cemento, bulto de 50 Kg | 8.4 | 39,900 | 335,160 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 482,471 |
| $153,842 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 5 | 5,200 | 26,000 |
Salario mínimo mensual vigente, base | 0.02 | 1,300,000 | 26,000 |
Transporte 1 tonelada x 1 kilómetro | 0.04 | 3,900 | 156 |
Salario mínimo mensual vigente, base | 0.00012 | 1,300,000 | 156 |
Valor Adicional: | 26,156 |
| $520,473 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 350 | 798 | 279,300 |
Cemento, bulto de 50 Kg | 7 | 39,900 | 279,300 |
Triturado de 3/4" x 1 m3 | 0.9 | 150,500 | 135,450 |
Grava 3/4" x 6 m3 | 0.150000003 | 903,000 | 135,450 |
Valor Adicional: | 471,761 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $435,423 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 300 | 798 | 239,400 |
Cemento, bulto de 50 Kg | 6 | 39,900 | 239,400 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 386,711 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $563,839 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 420 | 798 | 335,160 |
Cemento, bulto de 50 Kg | 8.4 | 39,900 | 335,160 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 482,471 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.125 | 578,347 | 72,293 |
Salario mínimo mensual vigente, incluyendo complementos | 0.0333375 | 2,168,530 | 72,293 |
Oficial de construcción x hora | 0.125 | 15,397 | 1,925 |
Salario mínimo mensual vigente, incluyendo complementos | 0.0008875 | 2,168,530 | 1,925 |
Valor Adicional: | 74,218 |
| $36 |
| $325,000 |
| $1,343,500 |
| $1,313,900 |
| $39,300 |