| $80,000 |
| $617,231,345 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-50 tipo perfil x 1 Kg | 35000 | 8,050 | 281,750,000 |
Soldador mano de obra x hora | 8750 | 16,640 | 145,600,000 |
Salario mínimo mensual vigente, base | 112 | 1,300,000 | 145,600,000 |
Valor Adicional: | 427,350,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Concreto (3000 psi) 20.7 MPa x 1 m3, mezclado en obra | 15 | 533,055 | 7,995,829 |
Arena lavada de río 1 m3 | 8.82 | 95,019 | 838,068 |
Cemento 1 Kg | 5512.5 | 798 | 4,398,975 |
Triturado de 3/4" x 1 m3 | 13.23 | 150,500 | 1,991,115 |
Agua para la obra 1 litro | 2992.5 | 36 | 108,927 |
Mezcladora 1 bulto, alquiler x hora | 7.2 | 7,150 | 51,480 |
Cuadrilla 7 (8 obreros) x jornal | 1.05 | 578,347 | 607,264 |
Acero G-60 x 1 Kg | 13000 | 5,200 | 67,600,000 |
Valor Adicional: | 75,595,829 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Replanteo Arquitectónico X 1 m2 | 200 | 10,038 | 2,007,529 |
Cuerda de Nylon 100 m x 0,50 mm | 10 | 50,900 | 509,000 |
Estaca de Madera Ø=0.05 L=0.60 m | 100 | 6,100 | 610,000 |
| 2 | 0 | 0 |
Cuadrilla de albañileria x 1 Hora | 3.28 | 24,504 | 80,374 |
| 0 | 0 | 0 |
Cuadrilla de albañileria x 1 Hora | 32.98 | 24,504 | 808,155 |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0 | 5,200 | 0 |
Estudio de suelos y geotecnia desde | 1 | 4,147,000 | 4,147,000 |
Perforación mecánica en suelo granular, incluye ensayos de clasificación metro a metro | 3 | 650,000 | 1,950,000 |
Ensayo SPT | 1 | 247,000 | 247,000 |
Informe Geotécnico y recomendaciones de construcción | 1 | 1,950,000 | 1,950,000 |
Valor Adicional: | 6,154,529 |
| $36 |
| $595,023 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 500 | 798 | 399,000 |
Cemento, bulto de 50 Kg | 10 | 39,900 | 399,000 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 546,311 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $30,900 |
| $46,000 |
| $325,000 |
| $17,472 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-60 x 1 Kg | 3.36 | 5,200 | 17,472 |
Valor Adicional: | 17,472 |
| $518,000 |
| $31,013 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-60 x 1 Kg | 5.964 | 5,200 | 31,013 |
Valor Adicional: | 31,013 |
| $107,328 |
| $56,500 |
| $390,000 |
| $94,910 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-60 x 1 Kg | 18.252 | 5,200 | 94,910 |
Valor Adicional: | 94,910 |
| $0 |
| $19,900 |
| $294,970 |
| $47,572,000 |
| $410,000 |
| $8,050 |
| $173,750 |
| $573,078 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 472.5 | 798 | 377,055 |
Cemento, bulto de 50 Kg | 9.45 | 39,900 | 377,055 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 524,366 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $57,750 |
| $576,791 |
| $116,600 |
| $63,200 |
| $2,915,000 |
| $126,000 |
| $38,350 |
| $106,550 |
| $98,250 |
| $50,450 |
| $53,400 |
| $55,000 |
| $90,700 |
| $42,250 |
| $67,050 |
| $73,650 |
| $72,150 |
| $98,250 |
| $33,000 |
| $83,750 |
| $112,600 |
| $48,500 |
| $260,000 |
| $153,842 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 5 | 5,200 | 26,000 |
Salario mínimo mensual vigente, base | 0.02 | 1,300,000 | 26,000 |
Transporte 1 tonelada x 1 kilómetro | 0.04 | 3,900 | 156 |
Salario mínimo mensual vigente, base | 0.00012 | 1,300,000 | 156 |
Valor Adicional: | 26,156 |
| $1,070,000 |
| $83,000 |
| $139,848 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Ladrillo Rejilla | 68 | 1,550 | 105,400 |
Mortero 1:4 (desperdicio 5%) x 1 m3 | 0.02 | 473,449 | 9,469 |
Arena lavada de río 1 m3 | 0.0256 | 95,019 | 2,432 |
Cemento 1 Kg | 7.64 | 798 | 6,097 |
Agua para la obra 1 litro | 4.8 | 36 | 175 |
Ayudante de construcción x 1 hora | 0.004 | 9,108 | 36 |
Ayudante de construcción x 1 hora | 0.08 | 9,108 | 729 |
Valor Adicional: | 114,869 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0.3675 | 5,200 | 1,911 |
Salario mínimo mensual vigente, base | 0.00147 | 1,300,000 | 1,911 |
Transporte 1 tonelada x 1 kilómetro | 0.04 | 3,900 | 156 |
Salario mínimo mensual vigente, base | 0.00012 | 1,300,000 | 156 |
Valor Adicional: | 2,067 |
| $27,016 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0.4 | 5,200 | 2,080 |
Salario mínimo mensual vigente, base | 0.0016 | 1,300,000 | 2,080 |
Transporte 1 tonelada x 1 kilómetro | 0.4 | 3,900 | 1,560 |
Salario mínimo mensual vigente, base | 0.0012 | 1,300,000 | 1,560 |
Valor Adicional: | 3,640 |
| $371,000 |
| $14,100 |
| $167,000 |
| $87,900 |
Los productos marcados con *** no estan disponibles en cantidad que quiere.