Descripción | Cantidad | Valor Unitario | Valor Total |
Perforación mecánica en suelo granular, incluye ensayos de clasificación metro a metro | 3 | 650,000 | 1,950,000 |
Salario mínimo mensual vigente, base | 1.5 | 1,300,000 | 1,950,000 |
Valor Adicional: | 1,950,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Informe Geotécnico y recomendaciones de construcción | 1 | 1,950,000 | 1,950,000 |
Salario mínimo mensual vigente, base | 1.5 | 1,300,000 | 1,950,000 |
Valor Adicional: | 1,950,000 |
| $247,000 |
| $1,950,000 |
| $2,499,000 |
| $6,845 |
| $1,427,500 |
| $2,380,250 |
| $1 |
| $445,300 |
| $75,000 |
| $234,000 |
| $533,055 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.588 | 95,019 | 55,871 |
Arena lavada de río 6 m3 | 0.0980196 | 570,000 | 55,871 |
Cemento 1 Kg | 367.5 | 798 | 293,265 |
Cemento, bulto de 50 Kg | 7.35 | 39,900 | 293,265 |
Triturado de 3/4" x 1 m3 | 0.882 | 150,500 | 132,741 |
Grava 3/4" x 6 m3 | 0.14700000294 | 903,000 | 132,741 |
Agua para la obra 1 litro | 199.5 | 36 | 7,262 |
Salario mínimo mensual vigente, base | 0.005586 | 1,300,000 | 7,262 |
Valor Adicional: | 489,139 |