Descripción | Cantidad | Valor Unitario | Valor Total |
Salario mínimo mensual vigente, incluyendo complementos | 7 | 2,168,530 | 15,179,710 |
Salario mínimo mensual vigente, base | 7 | 1,300,000 | 9,100,000 |
Salario mínimo mensual vigente, base | 0.8722 | 1,300,000 | 1,133,860 |
Salario mínimo mensual vigente, base | 0.84 | 1,300,000 | 1,092,000 |
Salario mínimo mensual vigente, base | 0.595 | 1,300,000 | 773,500 |
Salario mínimo mensual vigente, base | 0.63 | 1,300,000 | 819,000 |
Salario mínimo mensual vigente, base | 0.5831 | 1,300,000 | 758,030 |
Salario mínimo mensual vigente, base | 0.07 | 1,300,000 | 91,000 |
Salario mínimo mensual vigente, base | 0.0364 | 1,300,000 | 47,320 |
Salario mínimo mensual vigente, base | 0.5831 | 1,300,000 | 758,030 |
Salario mínimo mensual vigente, base | 0.2919 | 1,300,000 | 379,470 |
Salario mínimo mensual vigente, base | 0.175 | 1,300,000 | 227,500 |
Valor Adicional: | 15,179,710 |
| USD$35.66 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Ladrillo Rejilla | 68 | 1,550 | 105,400 |
Mortero 1:4 (desperdicio 5%) x 1 m3 | 0.02 | 473,449 | 9,469 |
Arena lavada de río 1 m3 | 0.0256 | 95,019 | 2,432 |
Cemento 1 Kg | 7.64 | 798 | 6,097 |
Agua para la obra 1 litro | 4.8 | 36 | 175 |
Ayudante de construcción x 1 hora | 0.004 | 9,108 | 36 |
Ayudante de construcción x 1 hora | 0.08 | 9,108 | 729 |
Valor Adicional: | 114,869 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0.3675 | 5,200 | 1,911 |
Salario mínimo mensual vigente, base | 0.00147 | 1,300,000 | 1,911 |
Transporte 1 tonelada x 1 kilómetro | 0.04 | 3,900 | 156 |
Salario mínimo mensual vigente, base | 0.00012 | 1,300,000 | 156 |
Valor Adicional: | 2,067 |
| USD$1.91 |
| USD$1,017.45 |
| USD$22.95 |
| USD$21.68 |
| USD$8.80 |
| USD$4,806.98 |
| USD$552.44 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Salario diario vigente | 50 | 43,329 | 2,166,450 |
Salario mínimo mensual vigente, base | 1.6665 | 1,300,000 | 2,166,450 |
Valor Adicional: | 2,166,450 |
| USD$59.32 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Sistema, Panel x 1 m2 x 0.04 m | 1.05 | 56,500 | 59,325 |
Malla plana RG2 | 0.4 | 5,350 | 2,140 |
Malla RGU 80 | 0.5 | 6,500 | 3,250 |
Malla angular RG1 | 0.5 | 6,700 | 3,350 |
Mortero 1:4 (desperdicio 5%) x 1 m3 | 0.055 | 473,449 | 26,040 |
Arena lavada de río 1 m3 | 0.0704 | 95,019 | 6,689 |
Cemento 1 Kg | 21.01 | 798 | 16,766 |
Agua para la obra 1 litro | 13.2 | 36 | 480 |
Ayudante de construcción x 1 hora | 0.011 | 9,108 | 100 |
Ayudante de construcción x 1 hora | 0.22 | 9,108 | 2,004 |
Barra de acero, varilla corrugada 1/2" G-60 número 4 | 0.258 | 31,013 | 8,001 |
Acero G-60 x 1 Kg | 1.538712 | 5,200 | 8,001 |
Valor Adicional: | 102,106 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 5 | 5,200 | 26,000 |
Salario mínimo mensual vigente, base | 0.02 | 1,300,000 | 26,000 |
Transporte 1 tonelada x 1 kilómetro | 0.04 | 3,900 | 156 |
Salario mínimo mensual vigente, base | 0.00012 | 1,300,000 | 156 |
Valor Adicional: | 26,156 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Muro panel doble cara x 1 m2 | 0.1 | 232,618 | 23,262 |
Sistema, Panel x 1 m2 x 0.04 m | 0.105 | 56,500 | 5,933 |
Malla plana RG2 | 0.04 | 5,350 | 214 |
Malla RGU 80 | 0.05 | 6,500 | 325 |
Malla angular RG1 | 0.05 | 6,700 | 335 |
Mortero 1:4 (desperdicio 5%) x 1 m3 | 0.0055 | 473,449 | 2,604 |
Barra de acero, varilla corrugada 1/2" G-60 número 4 | 0.0258 | 31,013 | 800 |
Cuadrilla de instalaciones x 1 Hora | 0.01508 | 26,955 | 406 |
Cuadrilla de instalaciones x 1 Hora | 0.1508 | 26,955 | 4,065 |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0.5 | 5,200 | 2,600 |
Transporte 1 tonelada x 1 kilómetro | 0.004 | 3,900 | 16 |
Muro panel doble cara x 1 m2 | 0.01 | 232,618 | 2,326 |
Muro panel doble cara x 1 m2 | 0.01 | 232,618 | 2,326 |
Muro panel doble cara x 1 m2 | 0.005 | 232,618 | 1,163 |
Muro panel doble cara x 1 m2 | 0.00064 | 232,618 | 149 |
Valor Adicional: | 23,262 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Muro panel doble cara x 1 m2 | 0.1 | 232,618 | 23,262 |
Sistema, Panel x 1 m2 x 0.04 m | 0.105 | 56,500 | 5,933 |
Malla plana RG2 | 0.04 | 5,350 | 214 |
Malla RGU 80 | 0.05 | 6,500 | 325 |
Malla angular RG1 | 0.05 | 6,700 | 335 |
Mortero 1:4 (desperdicio 5%) x 1 m3 | 0.0055 | 473,449 | 2,604 |
Barra de acero, varilla corrugada 1/2" G-60 número 4 | 0.0258 | 31,013 | 800 |
Cuadrilla de instalaciones x 1 Hora | 0.01508 | 26,955 | 406 |
Cuadrilla de instalaciones x 1 Hora | 0.1508 | 26,955 | 4,065 |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0.5 | 5,200 | 2,600 |
Transporte 1 tonelada x 1 kilómetro | 0.004 | 3,900 | 16 |
Muro panel doble cara x 1 m2 | 0.01 | 232,618 | 2,326 |
Muro panel doble cara x 1 m2 | 0.01 | 232,618 | 2,326 |
Muro panel doble cara x 1 m2 | 0.005 | 232,618 | 1,163 |
Muro panel doble cara x 1 m2 | 0.00064 | 232,618 | 149 |
Valor Adicional: | 23,262 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Muro panel doble cara x 1 m2 | 0.05 | 232,618 | 11,631 |
Sistema, Panel x 1 m2 x 0.04 m | 0.0525 | 56,500 | 2,966 |
Malla plana RG2 | 0.02 | 5,350 | 107 |
Malla RGU 80 | 0.025 | 6,500 | 163 |
Malla angular RG1 | 0.025 | 6,700 | 168 |
Mortero 1:4 (desperdicio 5%) x 1 m3 | 0.00275 | 473,449 | 1,302 |
Barra de acero, varilla corrugada 1/2" G-60 número 4 | 0.0129 | 31,013 | 400 |
Cuadrilla de instalaciones x 1 Hora | 0.00754 | 26,955 | 203 |
Cuadrilla de instalaciones x 1 Hora | 0.0754 | 26,955 | 2,032 |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0.25 | 5,200 | 1,300 |
Transporte 1 tonelada x 1 kilómetro | 0.002 | 3,900 | 8 |
Muro panel doble cara x 1 m2 | 0.005 | 232,618 | 1,163 |
Muro panel doble cara x 1 m2 | 0.005 | 232,618 | 1,163 |
Muro panel doble cara x 1 m2 | 0.0025 | 232,618 | 582 |
Muro panel doble cara x 1 m2 | 0.00032 | 232,618 | 74 |
Valor Adicional: | 11,631 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Muro panel doble cara x 1 m2 | 0.0064 | 232,618 | 1,489 |
Sistema, Panel x 1 m2 x 0.04 m | 0.00672 | 56,500 | 380 |
Malla plana RG2 | 0.00256 | 5,350 | 14 |
Malla RGU 80 | 0.0032 | 6,500 | 21 |
Malla angular RG1 | 0.0032 | 6,700 | 21 |
Mortero 1:4 (desperdicio 5%) x 1 m3 | 0.000352 | 473,449 | 167 |
Barra de acero, varilla corrugada 1/2" G-60 número 4 | 0.0016512 | 31,013 | 51 |
Cuadrilla de instalaciones x 1 Hora | 0.00096512 | 26,955 | 26 |
Cuadrilla de instalaciones x 1 Hora | 0.0096512 | 26,955 | 260 |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0.032 | 5,200 | 166 |
Transporte 1 tonelada x 1 kilómetro | 0.000256 | 3,900 | 1 |
Muro panel doble cara x 1 m2 | 0.00064 | 232,618 | 149 |
Muro panel doble cara x 1 m2 | 0.00064 | 232,618 | 149 |
Muro panel doble cara x 1 m2 | 0.00032 | 232,618 | 74 |
Muro panel doble cara x 1 m2 | 4.096E-5 | 232,618 | 10 |
Valor Adicional: | 1,489 |
| USD$21.09 |
| USD$907.80 |
| USD$39.23 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 5 | 5,200 | 26,000 |
Salario mínimo mensual vigente, base | 0.02 | 1,300,000 | 26,000 |
Transporte 1 tonelada x 1 kilómetro | 0.04 | 3,900 | 156 |
Salario mínimo mensual vigente, base | 0.00012 | 1,300,000 | 156 |
Valor Adicional: | 26,156 |
| USD$38.02 |
| USD$75.22 |
| USD$24.99 |
| USD$82.88 |
| USD$743.33 |
| USD$12.72 |
| USD$3,149.25 |
| USD$9.46 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Salario mínimo mensual vigente, incluyendo complementos | 0.0171 | 2,168,530 | 37,082 |
Salario mínimo mensual vigente, base | 0.0171 | 1,300,000 | 22,230 |
Salario mínimo mensual vigente, base | 0.00213066 | 1,300,000 | 2,770 |
Salario mínimo mensual vigente, base | 0.002052 | 1,300,000 | 2,668 |
Salario mínimo mensual vigente, base | 0.0014535 | 1,300,000 | 1,890 |
Salario mínimo mensual vigente, base | 0.001539 | 1,300,000 | 2,001 |
Salario mínimo mensual vigente, base | 0.00142443 | 1,300,000 | 1,852 |
Salario mínimo mensual vigente, base | 0.000171 | 1,300,000 | 222 |
Salario mínimo mensual vigente, base | 8.892E-5 | 1,300,000 | 116 |
Salario mínimo mensual vigente, base | 0.00142443 | 1,300,000 | 1,852 |
Salario mínimo mensual vigente, base | 0.00071307 | 1,300,000 | 927 |
Salario mínimo mensual vigente, base | 0.0004275 | 1,300,000 | 556 |
Valor Adicional: | 37,082 |
| USD$32.78 |
| USD$13.26 |
| USD$7.64 |
| USD$1,968.60 |
| USD$23.03 |
| USD$23.21 |
| USD$4,653.75 |
| USD$10.20 |
| USD$9.58 |
| USD$2,652.00 |
| USD$14.18 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Mortero 1:4 (desperdicio 5%) x 1 m3 | 0.01 | 473,449 | 4,734 |
Arena lavada de río 1 m3 | 0.0128 | 95,019 | 1,216 |
Cemento 1 Kg | 3.82 | 798 | 3,048 |
Agua para la obra 1 litro | 2.4 | 36 | 87 |
Ayudante de construcción x 1 hora | 0.002 | 9,108 | 18 |
Ayudante de construcción x 1 hora | 0.04 | 9,108 | 364 |
Bloque número 5 | 13.27 | 1,950 | 25,877 |
Valor Adicional: | 30,611 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0.3675 | 5,200 | 1,911 |
Salario mínimo mensual vigente, base | 0.00147 | 1,300,000 | 1,911 |
Transporte 1 tonelada x 1 kilómetro | 0.04 | 3,900 | 156 |
Salario mínimo mensual vigente, base | 0.00012 | 1,300,000 | 156 |
Valor Adicional: | 2,067 |