| $80,000 |
| $884,910 |
| $200,000 |
| $103,656 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Oficial de construcción x hora | 2 | 15,397 | 30,793 |
Salario mínimo mensual vigente, incluyendo complementos | 0.0142 | 2,168,530 | 30,793 |
Ayudante de construcción x 1 hora | 8 | 9,108 | 72,863 |
Salario mínimo mensual vigente, incluyendo complementos | 0.0336 | 2,168,530 | 72,863 |
Valor Adicional: | 103,656 |
| $4,998,000 |
| $1,300,000 |
| $31,013 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-60 x 1 Kg | 5.964 | 5,200 | 31,013 |
Valor Adicional: | 31,013 |
| $497,000 |
| $134,160 |
| $5,000,000 |
| $195,000 |
| $286,000 |
| $43,329 |
| $140,000 |
| $273,000 |
| $40,000 |
| $5,044,000 |
| $146,875 |
| $5,043 |
| $551,700 |
| $1,399,900 |
| $78,000 |
| $99,000 |
| $6,760 |
| $5,261,200 |
| $1,287,000 |
| $124,020 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-60 x 1 Kg | 23.85 | 5,200 | 124,020 |
Valor Adicional: | 124,020 |
| $3,234,351 |
| $25,000 |
| $2,119,000 |
| $83,900 |
| $1,250,000 |
| $78,000 |
| $2,119,000 |
| $1,235,000 |
| $1,520,000 |
| $30,000 |
| $812,000 |
| $2,600,000 |
| $380,000 |
| $578,347 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Salario mínimo mensual vigente, incluyendo complementos | 0.2667 | 2,168,530 | 578,347 |
Salario mínimo mensual vigente, base | 0.2667 | 1,300,000 | 346,710 |
Salario mínimo mensual vigente, base | 0.03323082 | 1,300,000 | 43,200 |
Salario mínimo mensual vigente, base | 0.032004 | 1,300,000 | 41,605 |
Salario mínimo mensual vigente, base | 0.0226695 | 1,300,000 | 29,470 |
Salario mínimo mensual vigente, base | 0.024003 | 1,300,000 | 31,204 |
Salario mínimo mensual vigente, base | 0.02221611 | 1,300,000 | 28,881 |
Salario mínimo mensual vigente, base | 0.002667 | 1,300,000 | 3,467 |
Salario mínimo mensual vigente, base | 0.00138684 | 1,300,000 | 1,803 |
Salario mínimo mensual vigente, base | 0.02221611 | 1,300,000 | 28,881 |
Salario mínimo mensual vigente, base | 0.01112139 | 1,300,000 | 14,458 |
Salario mínimo mensual vigente, base | 0.0066675 | 1,300,000 | 8,668 |
Valor Adicional: | 578,347 |
| $26,955 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Oficial de construcción x hora | 1.1 | 15,397 | 16,936 |
Salario mínimo mensual vigente, incluyendo complementos | 0.00781 | 2,168,530 | 16,936 |
Ayudante de construcción x 1 hora | 1.1 | 9,108 | 10,019 |
Salario mínimo mensual vigente, incluyendo complementos | 0.00462 | 2,168,530 | 10,019 |
Valor Adicional: | 26,955 |
| $249,000 |
| $325,000 |
| $7,999,000 |
| $299,000 |
| $347,000 |
| $15,397 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Salario mínimo mensual vigente, incluyendo complementos | 0.0071 | 2,168,530 | 15,397 |
Salario mínimo mensual vigente, base | 0.0071 | 1,300,000 | 9,230 |
Salario mínimo mensual vigente, base | 0.00088466 | 1,300,000 | 1,150 |
Salario mínimo mensual vigente, base | 0.000852 | 1,300,000 | 1,108 |
Salario mínimo mensual vigente, base | 0.0006035 | 1,300,000 | 785 |
Salario mínimo mensual vigente, base | 0.000639 | 1,300,000 | 831 |
Salario mínimo mensual vigente, base | 0.00059143 | 1,300,000 | 769 |
Salario mínimo mensual vigente, base | 7.1E-5 | 1,300,000 | 92 |
Salario mínimo mensual vigente, base | 3.692E-5 | 1,300,000 | 48 |
Salario mínimo mensual vigente, base | 0.00059143 | 1,300,000 | 769 |
Salario mínimo mensual vigente, base | 0.00029607 | 1,300,000 | 385 |
Salario mínimo mensual vigente, base | 0.0001775 | 1,300,000 | 231 |
Valor Adicional: | 15,397 |
| $9,108 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Salario mínimo mensual vigente, incluyendo complementos | 0.0042 | 2,168,530 | 9,108 |
Salario mínimo mensual vigente, base | 0.0042 | 1,300,000 | 5,460 |
Salario mínimo mensual vigente, base | 0.00052332 | 1,300,000 | 680 |
Salario mínimo mensual vigente, base | 0.000504 | 1,300,000 | 655 |
Salario mínimo mensual vigente, base | 0.000357 | 1,300,000 | 464 |
Salario mínimo mensual vigente, base | 0.000378 | 1,300,000 | 491 |
Salario mínimo mensual vigente, base | 0.00034986 | 1,300,000 | 455 |
Salario mínimo mensual vigente, base | 4.2E-5 | 1,300,000 | 55 |
Salario mínimo mensual vigente, base | 2.184E-5 | 1,300,000 | 28 |
Salario mínimo mensual vigente, base | 0.00034986 | 1,300,000 | 455 |
Salario mínimo mensual vigente, base | 0.00017514 | 1,300,000 | 228 |
Salario mínimo mensual vigente, base | 0.000105 | 1,300,000 | 137 |
Valor Adicional: | 9,108 |
| $83,000 |
| $299,000 |
| $595,023 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 500 | 798 | 399,000 |
Cemento, bulto de 50 Kg | 10 | 39,900 | 399,000 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 546,311 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $23,600 |
| $0 |
| $260,000 |
| $28,890 |
| $36 |
| $2,380,250 |
| $45,150 |
| $104,000 |
| $104,000 |
| $492,210 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Agua para la obra 1 litro | 179 | 36 | 6,516 |
Salario mínimo mensual vigente, base | 0.005012 | 1,300,000 | 6,516 |
Arena lavada de río 1 m3 | 0.756 | 95,019 | 71,834 |
Arena lavada de río 6 m3 | 0.1260252 | 570,000 | 71,834 |
Cemento 1 Kg | 315 | 798 | 251,370 |
Cemento, bulto de 50 Kg | 6.3 | 39,900 | 251,370 |
Triturado de 3/4" x 1 m3 | 0.756 | 150,500 | 113,778 |
Grava 3/4" x 6 m3 | 0.12600000252 | 903,000 | 113,778 |
Valor Adicional: | 443,498 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $75,000 |
| $435,423 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 300 | 798 | 239,400 |
Cemento, bulto de 50 Kg | 6 | 39,900 | 239,400 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 386,711 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $260,000 |
| $682,471 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 420 | 798 | 335,160 |
Cemento, bulto de 50 Kg | 8.4 | 39,900 | 335,160 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 482,471 |
| $28,000 |
| $95,000 |
| $27,250 |
| $184,900 |
| $39,500 |
| $104,000 |
| $284,350 |
| $97,500 |
| $50,000 |
| $182,000 |
| $104,000 |
| $96,642,307 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Concreto (3000 psi) 20.7 MPa x 1 m3, mezclado en obra | 51.58 | 533,055 | 27,494,990 |
Arena lavada de río 1 m3 | 30.32904 | 95,019 | 2,881,835 |
Cemento 1 Kg | 18955.65 | 798 | 15,126,609 |
Triturado de 3/4" x 1 m3 | 45.49356 | 150,500 | 6,846,781 |
Agua para la obra 1 litro | 10290.21 | 36 | 374,564 |
Mezcladora 1 bulto, alquiler x hora | 24.7584 | 7,150 | 177,023 |
Cuadrilla 7 (8 obreros) x jornal | 3.6106 | 578,347 | 2,088,180 |
Acero G-60 x 1 Kg | 2170 | 5,200 | 11,284,000 |
Cuadrilla de albañileria x 1 Hora | 800 | 24,504 | 19,603,511 |
Oficial de construcción x hora | 800 | 15,397 | 12,317,250 |
Ayudante de construcción x 1 hora | 800 | 9,108 | 7,286,261 |
Valor Adicional: | 58,382,502 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Concreto (3000 psi) 20.7 MPa x 1 m3, mezclado en obra | 5 | 533,055 | 2,665,276 |
Arena lavada de río 1 m3 | 2.94 | 95,019 | 279,356 |
Cemento 1 Kg | 1837.5 | 798 | 1,466,325 |
Triturado de 3/4" x 1 m3 | 4.41 | 150,500 | 663,705 |
Agua para la obra 1 litro | 997.5 | 36 | 36,309 |
Mezcladora 1 bulto, alquiler x hora | 2.4 | 7,150 | 17,160 |
Cuadrilla 7 (8 obreros) x jornal | 0.35 | 578,347 | 202,421 |
Acero G-60 x 1 Kg | 1300 | 5,200 | 6,760,000 |
Valor Adicional: | 9,425,276 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Replanteo Arquitectónico X 1 m2 | 200 | 10,038 | 2,007,529 |
Cuerda de Nylon 100 m x 0,50 mm | 10 | 50,900 | 509,000 |
Estaca de Madera Ø=0.05 L=0.60 m | 100 | 6,100 | 610,000 |
| 2 | 0 | 0 |
Cuadrilla de albañileria x 1 Hora | 3.28 | 24,504 | 80,374 |
| 0 | 0 | 0 |
Cuadrilla de albañileria x 1 Hora | 32.98 | 24,504 | 808,155 |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0 | 5,200 | 0 |
Estudio de suelos y geotecnia desde | 1 | 4,147,000 | 4,147,000 |
Perforación mecánica en suelo granular, incluye ensayos de clasificación metro a metro | 3 | 650,000 | 1,950,000 |
Ensayo SPT | 1 | 247,000 | 247,000 |
Informe Geotécnico y recomendaciones de construcción | 1 | 1,950,000 | 1,950,000 |
Valor Adicional: | 6,154,529 |
| $2,990,000 |
| $230,400 |
| $1,652,607 |
| $273,000 |
| $573,078 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 472.5 | 798 | 377,055 |
Cemento, bulto de 50 Kg | 9.45 | 39,900 | 377,055 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 524,366 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $1,500,000 |
| $473,449 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 1.28 | 95,019 | 121,624 |
Arena lavada de río 6 m3 | 0.213376 | 570,000 | 121,624 |
Cemento 1 Kg | 382 | 798 | 304,836 |
Cemento, bulto de 50 Kg | 7.64 | 39,900 | 304,836 |
Agua para la obra 1 litro | 240 | 36 | 8,736 |
Salario mínimo mensual vigente, base | 0.00672 | 1,300,000 | 8,736 |
Valor Adicional: | 435,196 |
| $12,038,000 |
| $26,700 |
| $97,500 |
| $69,900 |
| $207,000 |
| $104,000 |
| $78,500 |
| $130,000 |
| $180,000 |
| $57,750 |
| $650,000 |
| $132,000 |
| $48,500 |
| $90,700 |
| $315,000 |
| $150,900 |
| $533,100 |
| $525,950 |
| $83,750 |
| $664,500 |
| $208,000 |
| $95,019 |
| $145,500 |
| $340,807 |
| $89,500 |
| $55,000 |
| $71,200 |
| $43,750 |
| $69,450 |
| $1,574,907 |
| $260,000 |
| $386,450 |
| $29,600 |
| $54,750 |
| $56,200 |
| $29,050 |
| $123,400 |
| $1,346,500 |
| $34,000 |
| $28,250 |
| $33,400 |
| $21,850 |
| $390,000 |
Los productos marcados con *** no estan disponibles en cantidad que quiere.
De todas formas, puede comprar los que hay disponibles y el resto se lo enviamos mas tarde o esperar a que el stock este nuevamente disponible.