Descripción | Cantidad | Valor Unitario | Valor Total |
Oficial de construcción x hora | 2 | 15,397 | 30,793 |
Salario mínimo mensual vigente, incluyendo complementos | 0.0142 | 2,168,530 | 30,793 |
Ayudante de construcción x 1 hora | 8 | 9,108 | 72,863 |
Salario mínimo mensual vigente, incluyendo complementos | 0.0336 | 2,168,530 | 72,863 |
Valor Adicional: | 103,656 |
| USD$7.64 |
| USD$26.52 |
| USD$10.66 |
| USD$25.17 |
| USD$46.97 |
| USD$0.00 |
| USD$32.04 |
| USD$126.74 |
| USD$0.00 |
| USD$66.64 |
| USD$45.90 |
| USD$4.08 |
| USD$177.89 |
| USD$110.67 |
| USD$23.21 |
| USD$331.50 |
| USD$32.78 |
| USD$53.04 |
| USD$23.21 |
| USD$150.23 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.588 | 95,019 | 55,871 |
Arena lavada de río 6 m3 | 0.0980196 | 570,000 | 55,871 |
Cemento 1 Kg | 367.5 | 798 | 293,265 |
Cemento, bulto de 50 Kg | 7.35 | 39,900 | 293,265 |
Triturado de 3/4" x 1 m3 | 0.882 | 150,500 | 132,741 |
Grava 3/4" x 6 m3 | 0.14700000294 | 903,000 | 132,741 |
Agua para la obra 1 litro | 199.5 | 36 | 7,262 |
Salario mínimo mensual vigente, base | 0.005586 | 1,300,000 | 7,262 |
Valor Adicional: | 489,139 |