| USD$32.67 |
| USD$188.82 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 1.5185 | 95,019 | 144,286 |
Arena lavada de río 6 m3 | 0.25313395 | 570,000 | 144,286 |
Cemento 1 Kg | 656 | 798 | 523,488 |
Cemento, bulto de 50 Kg | 13.12 | 39,900 | 523,488 |
Agua para la obra 1 litro | 328.12 | 36 | 11,944 |
Salario mínimo mensual vigente, base | 0.00918736 | 1,300,000 | 11,944 |
Valor Adicional: | 679,718 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 3.675 | 5,200 | 19,110 |
Salario mínimo mensual vigente, base | 0.0147 | 1,300,000 | 19,110 |
Transporte 1 tonelada x 1 kilómetro | 0.4 | 3,900 | 1,560 |
Salario mínimo mensual vigente, base | 0.0012 | 1,300,000 | 1,560 |
Valor Adicional: | 20,670 |
| USD$12.72 |
| USD$32.61 |
| USD$10.84 |
| USD$22.19 |
| USD$44.42 |
| USD$11.07 |
| USD$7.97 |
| USD$61.20 |
| USD$12.51 |
| USD$6.32 |
| USD$361.59 |
| USD$35.90 |
| USD$14.98 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Canaleta 60 mm x 40 mm y 2 m de longitud | 0.5 | 42,500 | 21,250 |
Anclaje, chazo plástico 1/4" x 1 1/4" con tornillo, 1000 unidades | 0.0003 | 145,950 | 44 |
Cuadrilla de cableado estructurado x 1 hora | 0.54 | 43,329 | 23,398 |
Salario diario vigente | 0.54 | 43,329 | 23,398 |
Cuadrilla de cableado estructurado x 1 hora | 0.054 | 43,329 | 2,340 |
Salario diario vigente | 0.054 | 43,329 | 2,340 |
Cuadrilla de cableado estructurado x 1 hora | 0.27 | 43,329 | 11,699 |
Salario diario vigente | 0.27 | 43,329 | 11,699 |
Valor Adicional: | 58,730 |