| $83,750 |
| $308,000 |
| $51,750 |
| $30,700 |
| $266,000 |
| $58,730 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Canaleta 60 mm x 40 mm y 2 m de longitud | 0.5 | 42,500 | 21,250 |
Anclaje, chazo plástico 1/4" x 1 1/4" con tornillo, 1000 unidades | 0.0003 | 145,950 | 44 |
Cuadrilla de cableado estructurado x 1 hora | 0.54 | 43,329 | 23,398 |
Salario diario vigente | 0.54 | 43,329 | 23,398 |
Cuadrilla de cableado estructurado x 1 hora | 0.054 | 43,329 | 2,340 |
Salario diario vigente | 0.054 | 43,329 | 2,340 |
Cuadrilla de cableado estructurado x 1 hora | 0.27 | 43,329 | 11,699 |
Salario diario vigente | 0.27 | 43,329 | 11,699 |
Valor Adicional: | 58,730 |
| $116,600 |
| $73,650 |
| $650,000 |
| $292,000 |
| $67,700 |
| $27,650 |
| $664,500 |
| $99,000 |
| $260,000 |
| $45,500 |
| $121,800 |
| $0 |
| $1,249,890,200 |
| $83,200 |
| $207,400 |
| $85,500 |
| $130,000 |
| $440,000 |
| $104,000 |
| $260,000 |
| $187,800 |
| $111,550 |
| $7,684,100 |
| $221,150 |
| $707,325 |
| $29,600 |
| $93,900 |
| $65,650 |
| $30,900 |
| $63,100 |
| $105,300 |
| $297,050 |
| $2,456,850 |
| $130,750 |
| $30,200 |
| $131,900 |
| $189,950 |
| $62,050 |
| $130,000 |
| $73,000 |
| $397,750 |
| $37,700 |
| $212,750 |
| $105,300 |
| $95,000 |
| $96,500 |
| $130,000 |
| $101,400 |
| $310,900 |
| $293,700 |
| $36,650 |
| $249,300 |
| $127,900 |
| $93,700 |
| $72,900 |
| $4,810,000 |
| $338,000 |
| $80,500 |
| $140,400 |
| $43,400 |
| $102,700 |
| $1,018,750 |
| $210,000 |
| $140,800 |
| $328,000 |
| $226,000 |
| $1,620,000 |
| $78,000 |
| $69,000 |
| $430,000 |
| $247,000 |
| $39,000 |
| $174,200 |
| $106,600 |
| $13,000 |
| $350,000 |
| $52,900 |
| $39,850 |
| $1,075,000 |
| $65,900 |
| $12,507,952 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Sikaguard 68 Blanco Brillante | 2 | 699,000 | 1,398,000 |
Sikaplan®-12 NTR | 2 | 2,990,000 | 5,980,000 |
Sikatop - Seal 107 20 kilos | 6 | 184,900 | 1,109,400 |
Geotextil no tejido NT-1800 | 0.2 | 2,422,700 | 484,540 |
Valor Adicional: | 8,971,940 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Administración | 940000 | 1 | 940,000 |
Valor Adicional: | 940,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Imprevistos | 940000 | 1 | 940,000 |
Valor Adicional: | 940,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Utilidad | 470000 | 1 | 470,000 |
Valor Adicional: | 470,000 |
| $495,000 |
| $1,854,150 |
| $95,300 |
| $3,057,250 |
| $198,750 |
| $2,010,375,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Diseño de pavimento por unidad homogénea de diseño, según cbr y tránsito | 3 | 3,900,000 | 11,700,000 |
Salario mínimo mensual vigente, base | 9 | 1,300,000 | 11,700,000 |
Valor Adicional: | 11,700,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Subbase triturada de 2" x 1 m3 | 2100 | 125,200 | 262,920,000 |
Base granular de 1 1/2" x m3 | 2100 | 126,550 | 265,755,000 |
Asfalto 60/70 por tonelada | 700 | 2,100,000 | 1,470,000,000 |
Valor Adicional: | 1,998,675,000 |
| $533,055 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.588 | 95,019 | 55,871 |
Arena lavada de río 6 m3 | 0.0980196 | 570,000 | 55,871 |
Cemento 1 Kg | 367.5 | 798 | 293,265 |
Cemento, bulto de 50 Kg | 7.35 | 39,900 | 293,265 |
Triturado de 3/4" x 1 m3 | 0.882 | 150,500 | 132,741 |
Grava 3/4" x 6 m3 | 0.14700000294 | 903,000 | 132,741 |
Agua para la obra 1 litro | 199.5 | 36 | 7,262 |
Salario mínimo mensual vigente, base | 0.005586 | 1,300,000 | 7,262 |
Valor Adicional: | 489,139 |
| $25,200 |
| $78,700 |
| $47,250 |
| $32,050 |
| $54,650 |
| $368,000 |
| $50,600 |
| $29,000 |
| $43,400 |
| $26,350 |
| $31,950 |
Los productos marcados con *** no estan disponibles en cantidad que quiere.
De todas formas, puede comprar los que hay disponibles y el resto se lo enviamos mas tarde o esperar a que el stock este nuevamente disponible.