Descripción | Cantidad | Valor Unitario | Valor Total |
Diseño de pavimento por unidad homogénea de diseño, según cbr y tránsito | 3 | 3,900,000 | 11,700,000 |
Salario mínimo mensual vigente, base | 9 | 1,300,000 | 11,700,000 |
Valor Adicional: | 11,700,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Subbase triturada de 2" x 1 m3 | 2100 | 125,200 | 262,920,000 |
Base granular de 1 1/2" x m3 | 2100 | 126,550 | 265,755,000 |
Asfalto 60/70 por tonelada | 700 | 2,100,000 | 1,470,000,000 |
Valor Adicional: | 1,998,675,000 |
| $88,900 |
| $777,400 |
| $490,000 |
| $54,900 |
| $31,850 |
| $88,900 |
| $0 |
| $84,500 |
| $22,700 |
| $35,050 |
| $46,000 |
| $81,500 |
| $42,300 |
| $107,700 |
| $35,700 |
| $149,900 |
| $125,500 |
| $82,900 |
| $50,700 |
| $28,250 |
| $49,150 |
| $40,150 |
| $178,500 |
| $1,469,000 |
| $113,000 |
| $29,550 |
| $90,690 |
| $735,000 |
| $139,700 |
| $98,000 |
| $269,000 |
| $31,013 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-60 x 1 Kg | 5.964 | 5,200 | 31,013 |
Valor Adicional: | 31,013 |