| $672,283 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 1.0185 | 95,019 | 96,777 |
Arena lavada de río 6 m3 | 0.16978395 | 570,000 | 96,777 |
Cemento 1 Kg | 656 | 798 | 523,488 |
Cemento, bulto de 50 Kg | 13.12 | 39,900 | 523,488 |
Agua para la obra 1 litro | 328.12 | 36 | 11,944 |
Salario mínimo mensual vigente, base | 0.00918736 | 1,300,000 | 11,944 |
Valor Adicional: | 632,208 |
| $268,320 |
| $533,055 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.588 | 95,019 | 55,871 |
Arena lavada de río 6 m3 | 0.0980196 | 570,000 | 55,871 |
Cemento 1 Kg | 367.5 | 798 | 293,265 |
Cemento, bulto de 50 Kg | 7.35 | 39,900 | 293,265 |
Triturado de 3/4" x 1 m3 | 0.882 | 150,500 | 132,741 |
Grava 3/4" x 6 m3 | 0.14700000294 | 903,000 | 132,741 |
Agua para la obra 1 litro | 199.5 | 36 | 7,262 |
Salario mínimo mensual vigente, base | 0.005586 | 1,300,000 | 7,262 |
Valor Adicional: | 489,139 |
| $36 |
| $294,970 |
| $473,449 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 1.28 | 95,019 | 121,624 |
Arena lavada de río 6 m3 | 0.213376 | 570,000 | 121,624 |
Cemento 1 Kg | 382 | 798 | 304,836 |
Cemento, bulto de 50 Kg | 7.64 | 39,900 | 304,836 |
Agua para la obra 1 litro | 240 | 36 | 8,736 |
Salario mínimo mensual vigente, base | 0.00672 | 1,300,000 | 8,736 |
Valor Adicional: | 435,196 |
| $492,210 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Agua para la obra 1 litro | 179 | 36 | 6,516 |
Salario mínimo mensual vigente, base | 0.005012 | 1,300,000 | 6,516 |
Arena lavada de río 1 m3 | 0.756 | 95,019 | 71,834 |
Arena lavada de río 6 m3 | 0.1260252 | 570,000 | 71,834 |
Cemento 1 Kg | 315 | 798 | 251,370 |
Cemento, bulto de 50 Kg | 6.3 | 39,900 | 251,370 |
Triturado de 3/4" x 1 m3 | 0.756 | 150,500 | 113,778 |
Grava 3/4" x 6 m3 | 0.12600000252 | 903,000 | 113,778 |
Valor Adicional: | 443,498 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $31,013 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-60 x 1 Kg | 5.964 | 5,200 | 31,013 |
Valor Adicional: | 31,013 |
| $325,000 |
| $682,471 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 420 | 798 | 335,160 |
Cemento, bulto de 50 Kg | 8.4 | 39,900 | 335,160 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 482,471 |
| $130,000 |
| $573,078 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 472.5 | 798 | 377,055 |
Cemento, bulto de 50 Kg | 9.45 | 39,900 | 377,055 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 524,366 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |