| USD$24.37 |
| USD$58.78 |
| USD$127.47 |
| USD$16.14 |
| USD$483.19 |
| USD$5.28 |
| USD$23.32 |
| USD$125.51 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Agua para la obra 1 litro | 179 | 36 | 6,516 |
Salario mínimo mensual vigente, base | 0.005012 | 1,300,000 | 6,516 |
Arena lavada de río 1 m3 | 0.756 | 95,019 | 71,834 |
Arena lavada de río 6 m3 | 0.1260252 | 570,000 | 71,834 |
Cemento 1 Kg | 315 | 798 | 251,370 |
Cemento, bulto de 50 Kg | 6.3 | 39,900 | 251,370 |
Triturado de 3/4" x 1 m3 | 0.756 | 150,500 | 113,778 |
Grava 3/4" x 6 m3 | 0.12600000252 | 903,000 | 113,778 |
Valor Adicional: | 443,498 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| USD$17.26 |
| USD$35.60 |
| USD$33.15 |
| USD$135.93 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.588 | 95,019 | 55,871 |
Arena lavada de río 6 m3 | 0.0980196 | 570,000 | 55,871 |
Cemento 1 Kg | 367.5 | 798 | 293,265 |
Cemento, bulto de 50 Kg | 7.35 | 39,900 | 293,265 |
Triturado de 3/4" x 1 m3 | 0.882 | 150,500 | 132,741 |
Grava 3/4" x 6 m3 | 0.14700000294 | 903,000 | 132,741 |
Agua para la obra 1 litro | 199.5 | 36 | 7,262 |
Salario mínimo mensual vigente, base | 0.005586 | 1,300,000 | 7,262 |
Valor Adicional: | 489,139 |
| USD$9.13 |
| USD$7.05 |
| USD$364.01 |
| USD$13.20 |
| USD$5.18 |
| USD$15.56 |
| USD$5.80 |
| USD$369.75 |
| USD$9.15 |
| USD$5.76 |
| USD$5.94 |
| USD$179.01 |
| USD$27.18 |
| USD$12.72 |
| USD$7.57 |
| USD$6.46 |
| USD$9.31 |
| USD$74.89 |
| USD$14.17 |
| USD$7.99 |
| USD$151.73 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 500 | 798 | 399,000 |
Cemento, bulto de 50 Kg | 10 | 39,900 | 399,000 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 546,311 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| USD$21.80 |
| USD$7.83 |
| USD$13.49 |
| USD$174.03 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 420 | 798 | 335,160 |
Cemento, bulto de 50 Kg | 8.4 | 39,900 | 335,160 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 482,471 |
| USD$75.22 |
| USD$120.73 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 1.28 | 95,019 | 121,624 |
Arena lavada de río 6 m3 | 0.213376 | 570,000 | 121,624 |
Cemento 1 Kg | 382 | 798 | 304,836 |
Cemento, bulto de 50 Kg | 7.64 | 39,900 | 304,836 |
Agua para la obra 1 litro | 240 | 36 | 8,736 |
Salario mínimo mensual vigente, base | 0.00672 | 1,300,000 | 8,736 |
Valor Adicional: | 435,196 |
| USD$34.21 |
| USD$14.78 |
| USD$82.88 |
| USD$111.03 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 300 | 798 | 239,400 |
Cemento, bulto de 50 Kg | 6 | 39,900 | 239,400 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 386,711 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| USD$0.01 |
| USD$8.53 |
| USD$59.23 |
| USD$7.24 |
| USD$9.31 |
| USD$8.16 |
| USD$5.61 |
| USD$6.76 |
| USD$7.97 |
| USD$5.20 |
| USD$8.40 |
| USD$6.46 |
| USD$7.91 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-60 x 1 Kg | 5.964 | 5,200 | 31,013 |
Valor Adicional: | 31,013 |
| USD$11.48 |
| USD$17.48 |
| USD$4,323.33 |
| USD$44.93 |
| USD$12.50 |
| USD$146.14 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 472.5 | 798 | 377,055 |
Cemento, bulto de 50 Kg | 9.45 | 39,900 | 377,055 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 524,366 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| USD$5.52 |
| USD$132.72 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 350 | 798 | 279,300 |
Cemento, bulto de 50 Kg | 7 | 39,900 | 279,300 |
Triturado de 3/4" x 1 m3 | 0.9 | 150,500 | 135,450 |
Grava 3/4" x 6 m3 | 0.150000003 | 903,000 | 135,450 |
Valor Adicional: | 471,761 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| USD$23.41 |