| $130,000 |
| $1,560,000 |
| $36 |
| $88,550 |
| $28,200 |
| $520,000 |
| $69,700 |
| $24,850 |
| $4,549,600 |
| $156,000 |
| $650,000 |
| $2,777,000 |
| $156,000 |
| $76,650 |
| $492,210 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Agua para la obra 1 litro | 179 | 36 | 6,516 |
Salario mínimo mensual vigente, base | 0.005012 | 1,300,000 | 6,516 |
Arena lavada de río 1 m3 | 0.756 | 95,019 | 71,834 |
Arena lavada de río 6 m3 | 0.1260252 | 570,000 | 71,834 |
Cemento 1 Kg | 315 | 798 | 251,370 |
Cemento, bulto de 50 Kg | 6.3 | 39,900 | 251,370 |
Triturado de 3/4" x 1 m3 | 0.756 | 150,500 | 113,778 |
Grava 3/4" x 6 m3 | 0.12600000252 | 903,000 | 113,778 |
Valor Adicional: | 443,498 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $50,950 |
| $682,471 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 420 | 798 | 335,160 |
Cemento, bulto de 50 Kg | 8.4 | 39,900 | 335,160 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 482,471 |
| $6,921,250 |
| $26,100 |
| $1,250,000 |
| $435,423 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 300 | 798 | 239,400 |
Cemento, bulto de 50 Kg | 6 | 39,900 | 239,400 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 386,711 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $3,160,000 |
| $273,000 |
| $473,449 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 1.28 | 95,019 | 121,624 |
Arena lavada de río 6 m3 | 0.213376 | 570,000 | 121,624 |
Cemento 1 Kg | 382 | 798 | 304,836 |
Cemento, bulto de 50 Kg | 7.64 | 39,900 | 304,836 |
Agua para la obra 1 litro | 240 | 36 | 8,736 |
Salario mínimo mensual vigente, base | 0.00672 | 1,300,000 | 8,736 |
Valor Adicional: | 435,196 |
| $25,400 |
| $672,283 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 1.0185 | 95,019 | 96,777 |
Arena lavada de río 6 m3 | 0.16978395 | 570,000 | 96,777 |
Cemento 1 Kg | 656 | 798 | 523,488 |
Cemento, bulto de 50 Kg | 13.12 | 39,900 | 523,488 |
Agua para la obra 1 litro | 328.12 | 36 | 11,944 |
Salario mínimo mensual vigente, base | 0.00918736 | 1,300,000 | 11,944 |
Valor Adicional: | 632,208 |
| $1,170,000 |
| $325,000 |
| $29,850 |
| $650,000 |
| $520,473 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 350 | 798 | 279,300 |
Cemento, bulto de 50 Kg | 7 | 39,900 | 279,300 |
Triturado de 3/4" x 1 m3 | 0.9 | 150,500 | 135,450 |
Grava 3/4" x 6 m3 | 0.150000003 | 903,000 | 135,450 |
Valor Adicional: | 471,761 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $563,839 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 420 | 798 | 335,160 |
Cemento, bulto de 50 Kg | 8.4 | 39,900 | 335,160 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 482,471 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.125 | 578,347 | 72,293 |
Salario mínimo mensual vigente, incluyendo complementos | 0.0333375 | 2,168,530 | 72,293 |
Oficial de construcción x hora | 0.125 | 15,397 | 1,925 |
Salario mínimo mensual vigente, incluyendo complementos | 0.0008875 | 2,168,530 | 1,925 |
Valor Adicional: | 74,218 |
| $1,560,000 |
| $595,023 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 500 | 798 | 399,000 |
Cemento, bulto de 50 Kg | 10 | 39,900 | 399,000 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 546,311 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $66,500 |
| $573,078 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Arena lavada de río 1 m3 | 0.6 | 95,019 | 57,011 |
Arena lavada de río 6 m3 | 0.10002 | 570,000 | 57,011 |
Cemento 1 Kg | 472.5 | 798 | 377,055 |
Cemento, bulto de 50 Kg | 9.45 | 39,900 | 377,055 |
Triturado de 3/4" x 1 m3 | 0.6 | 150,500 | 90,300 |
Grava 3/4" x 6 m3 | 0.100000002 | 903,000 | 90,300 |
Valor Adicional: | 524,366 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Cuadrilla 7 (8 obreros) x jornal | 0.07 | 578,347 | 40,484 |
Salario mínimo mensual vigente, incluyendo complementos | 0.018669 | 2,168,530 | 40,484 |
Oficial de construcción x hora | 0.07 | 15,397 | 1,078 |
Salario mínimo mensual vigente, incluyendo complementos | 0.000497 | 2,168,530 | 1,078 |
Valor Adicional: | 41,562 |
| $2,663,050 |
| $1,560,000 |
| $32,500 |
| $1,220,700 |
| $294,970 |
| $544,900 |
| $121,250 |
| $20,000 |
| $28,600 |
| $97,500 |
| $21,100 |
| $33,400 |
| $78,700 |
| $220,050 |
| $565,500 |
| $45,500 |
| $39,250 |
| $82,200 |
| $25,200 |
| $34,250 |
| $32,900 |
| $469,700 |
| $43,400 |
| $41,400 |
| $102,700 |
| $616,700 |
| $20,900 |
| $250,400 |
| $444,750 |
| $1,340,900 |
| $325,500 |
| $32,050 |
| $1,313,900 |
| $199,700 |
| $124,020 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Acero G-60 x 1 Kg | 23.85 | 5,200 | 124,020 |
Valor Adicional: | 124,020 |
| $157,000 |
| $63,100 |
| $1,343,500 |
| $140,600 |
| $261,100 |
| $102,100 |
| $2,499,000 |
| $1 |
| $4,737,700 |
| $12,507,952 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Sikaguard 68 Blanco Brillante | 2 | 699,000 | 1,398,000 |
Sikaplan®-12 NTR | 2 | 2,990,000 | 5,980,000 |
Sikatop - Seal 107 20 kilos | 6 | 184,900 | 1,109,400 |
Geotextil no tejido NT-1800 | 0.2 | 2,422,700 | 484,540 |
Valor Adicional: | 8,971,940 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Administración | 940000 | 1 | 940,000 |
Valor Adicional: | 940,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Imprevistos | 940000 | 1 | 940,000 |
Valor Adicional: | 940,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Utilidad | 470000 | 1 | 470,000 |
Valor Adicional: | 470,000 |
| $121,400 |
| $48,200 |
| $650,000 |
| $0 |
| $75,000 |
| $416,000 |
| $5,200 |
| $58,500 |
| $112,970 |
| $1,950,000 |
| $286,000 |
| $2,990,000 |
| $97,500 |
| $35,200 |
| $34,050 |
| $2,990,000 |
| $2,380,250 |
| $31,600 |
| $4,147,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Perforación mecánica en suelo granular, incluye ensayos de clasificación metro a metro | 3 | 650,000 | 1,950,000 |
Salario mínimo mensual vigente, base | 1.5 | 1,300,000 | 1,950,000 |
Valor Adicional: | 1,950,000 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Informe Geotécnico y recomendaciones de construcción | 1 | 1,950,000 | 1,950,000 |
Salario mínimo mensual vigente, base | 1.5 | 1,300,000 | 1,950,000 |
Valor Adicional: | 1,950,000 |
| $305,000 |
| $650,000 |
| $268,000 |