Descripción | Cantidad | Valor Unitario | Valor Total |
Agua para la obra 1 litro | 3.5 | 36 | 127 |
Salario mínimo mensual vigente, base | 9.8E-5 | 1,300,000 | 127 |
Pegacor max, 25 Kg, porcelanato | 0.25 | 85,500 | 21,375 |
Porcelanato sellado Beige x 1 m2 | 1 | 135,900 | 135,900 |
Valor Adicional: | 157,402 |
| USD$9.15 |
| USD$9.03 |
| USD$20.35 |
| USD$23.21 |
| USD$6.35 |
| USD$14.51 |
| USD$10.77 |
| USD$160.50 |
| USD$8.80 |
| USD$75.22 |
| USD$12.76 |
| USD$9.24 |
| USD$16.65 |
| USD$22.14 |
Descripción | Cantidad | Valor Unitario | Valor Total |
Transporte 1 metro cúbico por 1 kilómetro m3/Km | 0.2 | 5,200 | 1,040 |
Salario mínimo mensual vigente, base | 0.0008 | 1,300,000 | 1,040 |
Transporte 1 tonelada x 1 kilómetro | 0.04 | 3,900 | 156 |
Salario mínimo mensual vigente, base | 0.00012 | 1,300,000 | 156 |
Valor Adicional: | 1,196 |
| USD$3.44 |
| USD$0.00 |
| USD$166.77 |